Construction is well underway for the new Third Street Suites North Residence Hall. Third Street Suites will offer suite-style units, similar to the original Third Street. Located near central campus and just behind the Black Cultural Center, you'll be steps away from retail dining locations including Starbucks and Third Street Market. Wiley Dining Court is also just a short walk via sidewalks (no need to cross the street!). Also close by is the Purdue Co-Rec and convenient bus stops to get you where you need to go.

Follow the progress via a live webcam!

WEEK OF DECEMBER 6TH:

  • Masonry (brick) continues on the south side of building B (up to the fifth floor, now).
  • Inside, drywall and sanding continues - the student rooms are starting to take shape!
  • We continue to work on making the building site ready for winter weather (exterior sheething, water-tight inspections).
  • DID YOU KNOW? When students return from winter break, we'll be painting and tiling inside student rooms. Construction is on-schedule for Fall 2020 move-in. 

WEEK OF NOVEMBER 18TH:

  • Mechanical, electrical, plumbing and fire protection activities are still ongoing within the building.
  • Drywall continues inside the building.
  • Masonry continues on the south side of the north portion of the building, as well as the west side of the south portion of the building.
  • DID YOU KNOW? The average electrician on the job takes approximately 16,000 steps during a work day.

WEEK OF NOVEMBER 11TH:

  • Winter protection (enclosing the building) is nearly complete.
  • Drywall work continues.
  • Temporary heat has been brought in to keep the inside of the building at 50 degrees while work continues during the winter months.

WEEK OF NOVEMBER 4TH:

  • IMPORTANT: Due to the upcoming weather conditions, there may be work occurring on Saturdays and Sundays in order to stay on schedule.
  • Brick on the west side of the south pod has started.
  • Drywall is going in on the second floor of the south pod.
  • DID YOU KNOW? There are approximately 380,000 bricks being laid for Third Street North!

WEEK OF OCTOBER 21ST:

  • Crews are installing insulation from the bottom up.
  • Drywall is also being installed this week! Look out for deliveries of drywall pieces.
  • Permanent power is expected to be up and running this week.

WEEK OF OCTOBER 14TH:

  • Pipes will go through hydronic testing. This means the pipes will be tested to ensure proper water movement flows through the heating, ventilation and air conditioning (HVAC) system.
  • Exterior framing of the ground floor is now complete.
  • The exterior brick will be getting washed soon, so be on the lookout for the fresh-looking exterior of Third Street North!
  • DID YOU KNOW? The masons will put up a barrier during the winter to warm up the area they are working on. This will help keep the grout at the correct temperature so they can continue working through freezing temperatures this winter.

WEEK OCTOBER 7TH:

  • 100% of the individual window units (student rooms) have been installed!
  • Drywall framing has begun on the south portion of the 6th floor.
  • Framing for the elevators will begin soon!
  • DID YOU KNOW? Approximately 53,548 hours of labor have been put into construction of this building, so far!

WEEK OF SEPTEMBER 23RD:

  • Heating and cooling units will start to be installed into the individual rooms!
  • The brick interior work continues along the east side of the building (along Russell Street).
  • Windows are being installed in the residence hall rooms.
  • DID YOU KNOW? The height of Third Street North, from the bottom of the ground floor, to the top of the penthouse, will be 77'5"!

WEEK OF SEPTEMBER 16TH:

  • Major milestone: roofing starts this week! Then, around October 1st, drywall is expected to begin as work on Third Street North moves inside.
  • Reminder: Construction hours are 7 a.m. to 7 p.m.
  • DID YOU KNOW: The freight elevators at the construction site are pink - for a reason! For breast cancer awareness. 

WEEK OF SEPTEMBER 9TH:

  • Construction hours are from 7 a.m. to 7 p.m. unless otherwise announced.
  • OUTSIDE: Sitework for the water main is expected to be completed.
  • INSIDE: In-wall plumbing continues throughout the south section of the building, and electrical rough-in will be finishing up on the 3rd floor in far northern section of the building.
  • DID YOU KNOW? Third Street Suites North will be a LEED certified building!

Updates provided by:

Jared King

Jared King

Third Street Suites North Construction Advocate

Construction Management Technology (Class of 2021)

"Hi! I'm Jared, the Construction Advocate for Third Street Suites North. I chose to major in Construction Management Technology because the construction industry will always be around. I think it's also exciting to look at a building and say "I had a part in that." I love Purdue because it is a university of hard-working people that are all trying to work toward a better future."